The National Plan of Integrated Airport Systems (NPIAS) identifies nearly 3,400 existing and proposed airports that are significant to national air transportation and thus eligible to receive Federal grants under the Airport Improvement Program (AIP). The NPIAS contains all commercial service airports, all reliever airports and selected general aviation airports. It also includes estimates of the amount of AIP money needed to fund infrastructure development projects that will bring these airports up to current design standards and add capacity to congested airports. The FAA is required to provide Congress with a 5-year estimate of AIP eligible development every two years. Below is a summary of projects that are anticipated for the 20-year planning period.

Site NameProject DescriptionAdditional InformationRunwayEstimated Project CostYear Range
Ardmore Downtown Executive Install Perimeter Fencing Fence 1,408,000 1 - 5
Ardmore Downtown Executive Rehabilitate Runway 17/35 17/35 4,000,000 1 - 5
Ardmore Downtown Executive Reconstruct Apron Aprons 1,685,000 1 - 5
Ardmore Downtown Executive Acquire Land For Approaches North RPZ 400,000 1 - 5
Ardmore Downtown Executive Construct Terminal Building Terminal 2,500,000 1 - 5
Ardmore Downtown Executive Acquire Land for Development 225,000 11 - 20
Ardmore Downtown Executive Rehabilitate Runway 17-35 Reconstruct 17/35 3,835,000 11 - 20
Ardmore Downtown Executive Rehabilitate Taxiway Parallel TW 365,000 11 - 20
Ardmore Downtown Executive Construct Taxiway Taxilanes 920,000 11 - 20
Ardmore Downtown Executive Update Airport Master Plan Study Master Plan 260,000 11 - 20
Ardmore Downtown Executive Construct Hangar Building Hangars 3,860,000 11 - 20
Ardmore Downtown Executive Improve Runway 35 Safety Area 600,000 11 - 20
Ardmore Downtown Executive Install Weather Reporting Equipment (AWOS) AWOS 325,000 11 - 20
Ardmore Downtown Executive Construct Taxiway Taxilanes 760,000 6 - 10
Ardmore Downtown Executive Construct Service Road 180,000 6 - 10
Ardmore Downtown Executive Rehabilitate Taxiway Parallel TW 600,000 6 - 10
Ardmore Downtown Executive Remove Obstructions Obstructions 2,210,000 6 - 10
Ardmore Downtown Executive Construct Hangar Building Hangars 4,110,000 6 - 10