I-344/John Kilpatrick Turnpike lane closures at Council Rd. through 2026
The following lane closures will impact traffic on the I-344/John Kilpatrick Turnpike at Council Rd.:
- Westbound I-344/John Kilpatrick Turnpike will be narrowed near Council Road (mm 122) from 7 p.m. Monday to 5 a.m. Tuesday and 7 p.m. Tuesday to 5 a.m. Wednesday for bridge construction operations.
- Eastbound I-344/John Kilpatrick Turnpike will be narrowed near Council Road (122) from 7 p.m. Wednesday to 5 a.m. Thursday and from 7 p.m. Thursday and to 5 a.m. Friday for bridge construction operations.
- Eastbound Memorial Rd. will be narrowed to one lane between Council Rd. and Rockwell Ave. through 2026 for construction of the new lane and the new on-ramp to I-344/John Kilpatrick Turnpike.
- Northbound and southbound Council Rd. lanes will be narrowed and shifted between just north of westbound Memorial Rd. and just south of eastbound Memorial Rd. through 2026 for construction of protected turnaround lanes
I-344/John Kilpatrick Turnpike sweeping operations Monday overnight
I-344/John Kilpatrick Turnpike will have intermittent lane closures overnight for roadway sweeping from 8 p.m. Monday to 4:30 a.m. Tuesday. Motorists should use caution in the area.
SH-351/Muskogee Turnpike narrows near SH-165 interchange on Tuesday
Westbound (going north) SH-351/Muskogee Turnpike will be narrowed near SH-165 interchange (mm 37) from 8 a.m. to 3 p.m. Tuesday for concrete repairs.
SH-364/Creek Turnpike narrows near Jenks Tuesday, Wednesday
Eastbound and westbound SH-364/Creek Turnpike will be narrowed to two lanes in each direction half a mile from the Riverside Parkway interchange near Jenks (mm 8) from 9 a.m. to 5 p.m. Tuesday and from 9 a.m. to 5 p.m. Wednesday for utility work.
I-44/Will Rogers Turnpike narrows near Afton on Tuesday
Westbound I-44/Will Rogers Turnpike will be narrowed 3 miles west of the US-60 interchange near Afton (mm 299) from 8:30 a.m. to 1:30 p.m. Tuesday for barrier wall repairs.
I-44/H.E. Bailey Turnpike narrows between Chickasha and Newcastleon Tuesday
Westbound I-44/H.E. Bailey Turnpike will be narrowed 5 miles west of SH-4 between Chickasha and Newcastle (mm 94) from 8 a.m. to 3 p.m. Tuesday for concrete repairs.
SH-344/Gilcrease Turnpike narrows near US-412 on Tuesday
Southbound SH-344/Gilcrease Turnpike will be narrowed just south of US-412 (mm 5) from noon to 4 p.m. Tuesday for bridge joint repairs.
I-44 narrows at SH-37 in Newcastle Monday night for striping
Eastbound and westbound I-44 (runs north and south) will be narrowed to one lane in each direction at SH-37 (mm 108) in Newcastle from 7 p.m. Monday to 6 a.m. Tuesday for striping in the work zone for the I-44/US-62/SH-37 interchange construction to connect to the Toby Keith Expressway. I-44 lanes will be slightly narrowed for the duration of the nearly two-year construction project.
SH-375/Indian Nation Turnpike narrows near I-40 interchange on Tuesday
Southbound SH-375/Indian Nation Turnpike will be narrowed at the I-40 interchange (mm 103-104) from 8 a.m. to 3 p.m. Tuesday for shoulder repairs.
SH-375/Indian Nation Turnpike narrows near McAlester through Nov. 24
Southbound SH-375/Indian Nation Turnpike will be narrowed near McAlester, 2 miles south of US-270 (mm 67) through 10 a.m. Tuesday, Nov. 24, for bridge joint repairs.
Portland Ave. closes at N.W. 24th St. in Newcastle; speed limit reduced on I-44 frontage roads
Northbound and southbound Portland Ave. is closed between N.W. 24th St. and N.E. 34th St. in Newcastle through late 2027 for bridge construction related to the new Toby Keith Expressway interchange at I-44/US-62 and SH-37.
Additionally, the northeast and southeast I-44 frontage roads will have reduced speed limits between N.E. 24th St. and N.E. 34th St. through late 2027. Watch for workers in the area as work has started in portions of the right-of-way along the frontage roads.
I-344/John Kilpatrick Turnpike intermittent lane shifts through spring 2027
I-344/John Kilpatrick Turnpike will be widened to six lanes between W. Wilshire Blvd. (mm 116) to half a mile north of N.W. 122nd St. (mm 120). Traffic will be shifted and have a narrowed lane width, but the turnpike will remain open to two lanes in each direction. Northwest and southeast SH-3/N.W. Expressway will be narrowed between County Line Rd. and Morgan Rd. through late spring 2027 for bridge work above the highway.
I-44/Turner Turnpike bridge reconstruction at Arcadia Lake
I-44/Turner Turnpike bridge reconstruction at mm 136 between I-35 and Midwest Boulevard will replace the existing twin bridges with a single bridge built for the turnpike's future six lanes. Two lanes of traffic in each direction will be open during construction, but motorists can expect lane shifts throughout the project through spring 2027.
US-312/Cimarron Turnpike Spur narrowed for bridge rehab through fall 2026
This project rehabilitates the US-312/Cimarron Turnpike Spur bridge over US-177 (mm 19-20) near Stillwater. Motorists are reminded to stay alert in the work zone and to expect shifted lanes through fall 2026.
SH-364/Creek Turnpike traffic shifts to new Haikey Creek bridge; 96th St. ramp remains closed
Eastbound and westbound SH-364/Creek Turnpike traffic is shifted onto the new Haikey Creek bridge and will be reduced to one lane between US-64 and E. 111th St. (mm 14-15) in Broken Arrow.
The eastbound SH-364/Creek Turnpike on-ramp from 96th St. is closed through fall 2026 to safely facilitate construction. Motorists should expect delays in the area through summer 2027.
SH-364/Creek Turnpike shoulder narrows near Broken Arrow
SH-364/Creek Turnpike westbound shoulder to close near Broken Arrow between Aspen Avenue and Elm Place (mm 18) for retaining wall repairs along the Liberty Trail. This project is estimated to be completed in mid-December 2026.
SH-351/Muskogee Turnpike narrows between SH-165 and I-40 for shoulder reconstruction
SH-351/Muskogee Turnpike traffic has been shifted to head-to-head traffic in the southbound lanes between SH-165 (mm 37) near Muskogee and I-40 (mm 56) near Webbers Falls while construction takes place in the northbound lanes; at the beginning of September, construction will shift to the southbound lanes and traffic will transfer to the northbound lanes. Closures will take place in 5-mile segments, and work is expected to be completed by fall 2026. This project is for shoulder reconstruction, which includes milling and overlaying the existing asphalt shoulder and reconstructing the guardrail.
I-44/H.E. Bailey Turnpike narrows between Walters and Geronimo for pavement reconstruction
Northbound and southbound I-44/H.E. Bailey Turnpike will be narrowed to one lane in each direction between US-277/SH-5 near Walters and SH-36 near Geronimo (mm 20-30) for pavement reconstruction.
SH-375/Indian Nation Turnpike is narrowed to one lane near SH-63 and Blanco
Northbound and southbound SH-375/Indian Nation Turnpike will be narrowed to one lane in each direction at SH-63 near Blanco (mm 55) for the construction of a new interchange. Additionally, SH-63 is narrowed to one lane. Temporary signals are being utilized in the work zone. This project is estimated to be completed in early 2027.
Ragan Rd. narrows at SH-375/Indian Nation Turnpike for interchange improvement through 2026
Northbound and southbound SH-375/Indian Nation Turnpike is narrowed to one lane in each direction near Indianola (mm 81-82) while new ramps are under construction. Additionally, Ragan Rd. is reduced to one lane in both directions. This nearly $5 million project reconstructs the existing half-diamond interchange to a full-diamond interchange. Work is expected to be completed in late 2026.