Plan Ahead for I-35 Corridor Construction and Delays, Consider Alternate Route

View map of current interstate traffic conditions at www.oktraffic.org

Download the free Drive Oklahoma app for your Apple or Android phone.

*Check the latest traffic advisories for maintenance closures at https://oklahoma.gov/odot/citizen/traffic-advisories.html

I-35 bridge rehabilitation near Tonkawa – Kay Co.

Impact to Traffic

  • I-35 is narrowed to one lane in each direction between US-60 (mm 214) and SH-15 (mm 203) near Tonkawa.
  • The speed limit is reduced in the work zone.

 About the Project

  • Nearly $2 million contract awarded to Logos Construction Co., of Sapulpa
  • Project includes rehabilitation of the I-35 bridges over the Salt Fork of the Arkansas River near Tonkawa. The work is focused on repairing the substructures of the bridges and bridge joints. While the work may not be visible to motorists at times, the lane closures are necessary to help protect the crews and equipment working underneath the bridge.
  • Work is expected to be completed in summer 2021.

 

I-35 bridge rehabilitation & ramp reconstruction in Goldsby - McClain Co.

Impact to Traffic

  • North and southbound I-35 will be intermittently narrowed to one lane at SH-74 South (mm 104) in Goldsby during overnight hours nightly through spring 2021.
  • Motorists exiting southbound I-35 to SH-74 South/Main St. have the choice between two off-ramps which both lead to SH-74 South/Goldsby:
    • Drivers can exit using the original off-ramp to Interstate Dr., located north of the SH-74 bridge over I-35, which connects to SH-74 South/Main St. to the south; or 
    • Drivers can exit to the new loop off-ramp SH-74 South, which is located just south of the SH-74 bridge over I-35. Exiting traffic must come to a stop at the end of the ramp before turning onto SH-74 South/Main St.
  • The northbound I-35 off-ramp to SH-74 South/Main St. will remain open throughout the project; however the ramp is shifted and requires a stop at SH-74 South.
  • I-35 on- and off-ramps will be narrowed with flaggers directing traffic at times. 
  • SH-74 South/Main St. will be intermittently narrowed to one lane with a temporary traffic signal between Airport Rd. and Center Rd.
  • The speed limit is reduced in the work zone

About the Project

  • $4.8 million contract awarded to Allen Contracting, of Oklahoma City
  • Project will rehabilitate the SH-74 South bridge across I-35 and reconstruct the ramps at I-35 and SH-74 South, including a new roundabout
  • Work is expected to be completed in spring 2021

 

I-35 bridge rehabilitation in Pauls Valley - Garvin Co.

Impact to Traffic

  • I-35 is narrowed to one lane in each direction at SH-19 (mm 72) in Pauls Valley through summer 2021.

About the Project

  • $3.5 million contract awarded to Silver Star Construction Co., Inc., of Moore
  • Project includes rehabilitation of the I-35 bridges over SH-19 in two phases. The northbound bridge was completed in 2020. The southbound bridge will be rehabilitated in spring 2021.
  • All work is expected to be completed in summer 2021.
 
 
 

I-35 bridge rehabilitation near Davis - Murray/Garvin Co.  

Impact to Traffic

  • I-35 is narrowed to one lane in each direction just north of SH-7 (mm 56) between Davis and Wynnewood through summer 2021.
  • The speed limit is reduced in the work zone

About the Project

  • More than $1 million contract awarded to B&B Construction, of Clayton, Okla.
  • Project includes rehabilitation of I-35 bridges over Wildhorse Creek Overflow
  • Work is expected to be completed in summer 2021.

 

 

I-35 sign replacement between Davis and Thackerville - Murray/Carter/Love Co.

Impact to Traffic

  • Drivers can expect various intermittent shoulder closures on north and southbound I-35 at various locations between SH-7 (mm 55) near Davis and the Texas state line (mm 1) near Thackerville through spring 2021.
  • I-35 will be narrowed to one lane in each direction between US-70 West (mm 31) and SH-142 East (mm 33) in Ardmore in Carter County from 7 a.m. to 5:30 p.m. daily Monday through Thursday and from 6 a.m. to noon Friday through spring 2021 for ongoing sign installation. All lanes will be open to traffic Friday afternoon through Sunday.

About the Project

  • Nearly $3 million contract awarded to Action Safety Supply Co., of Oklahoma City
  • Project includes replacement of outdated I-35 signage at multiple locations in southern Oklahoma
  • Work is expected to be completed in spring 2021

Learn about future I-35 improvements scheduled in ODOT's Eight-year Construction Work Plan